Do you still have a terrible headache about upcoming 070-178? Let our 070-178 real exam questions and 070-178 test dumps vce pdf help you pass exam easily. Don't worry! Just 1-2 days' preparation before real test, easily pass 070-178 exam! Can you believe it? Leave it to the professional!
We Real4dumps helped more 5800 candidates pass 070-178 exam since the year of 2009. All of real exam dumps experts have more than 10 years' working experience who worked for the international large companies such as Cisco, Microsoft, SAP, Oracle and so on. Based on past data our passing rate for 070-178 exam is high to 99.52% with our real exam questions and test dumps vce pdf.
Instant Download: Upon successful payment, Our systems will automatically send the product you have purchased to your mailbox by email. (If not received within 12 hours, please contact us. Note: don't forget to check your spam.)
We provide you three versions of our real exam dumps:
1.The PDF Version: If you are used to reading and writing questions and answers on paper, you can choose the dumps vce pdf files of 070-178 real exam questions and 070-178 test dumps vce pdf. It is available for reading on-line and printing out for practice.
2.The Software Version: If you are used to study on windows computer, you can choose the software version of 070-178 real exam questions and 070-178 test dumps vce pdf. It is interactive and functional. It reminds you good study methods and easy memorization. If you make mistakes after finishing the real exam dumps the software will remember your mistakes and notice you practice many times.
3.The On-line Version: Its functions are the same with software version. The difference is that the on-line version of 070-178 real exam questions and 070-178 test dumps vce pdf is used on downloading into all operate system computers, mobile phone and others. The software is only available in windows PC computer. You can read, write and recite at any time and any places if you want. Studying is easy and interesting.
Sometimes we know from our customers that their friends or colleagues give up exams in despair as they fail exams several times. We feel sorry to hear that and really want to help them with our 070-178 real exam questions and 070-178 test dumps vce pdf (Microsoft Project 2010, Managing Projects). But they refuse to attend the exam again. Choices are more important than efforts.
We not only provide you the best 070-178 real exam questions and 070-178 test dumps vce pdf but also good service.
1.Our customer service is 7/24 on-line. Whenever you have any questions we will be pleased to solve for you or help you in the first time.
2.As of the date of purchasing we provide you one-year service warranty. Our IT department colleagues check update information every day. When 070-178 real exam dumps update we will send you the download emails for your reference. If you pass exam you can share with your friends or colleagues.
3.We promise to keep your information in secret and safe. We have a strict information protection system so you should not worry about this. Also we won't send advertisement emails to you too.
4.We guarantee 100% pass 070-178 exam (Microsoft Project 2010, Managing Projects). If you fail the exam we will refund you the full dumps costs. You send the failure score certification to our support email. Once confirmed we will refund you two days except of official holidays.
5.We provide real exam dumps discounts for old customers and long-term cooperation companies. If you have interest please contact with us.
In the end, if you still have any other doubt about our 070-178 real exam questions and 070-178 test dumps vce pdf please contact with us we will reply you ASAP. Our team will serve for you at our heart and soul. We are the best. Trust me. Choosing us will be helpful for your exams. Come on! 100% pass exam.
Microsoft 070-178 Exam Syllabus Topics:
| Section | Objectives |
|---|---|
| Executing Projects | - Project execution tracking in Microsoft Project
|
| Monitoring and Controlling Projects | - Schedule and performance control
|
| Closing Projects | - Project closure activities
|
| Planning Projects | - Project scheduling and task planning in Microsoft Project 2010
|
| Initiating Projects | - Defining project scope and objectives
|
Microsoft Project 2010, Managing Projects Sample Questions:
Question 1
You want to print the Gantt Chart view of your project. You need to hide the Gantt chart legend. What should you do?
A. Edit the layout.
B. Edit the Page Setup dialog box.
C. Edit the Bar Styles dialog box.
D. Edit the view.
E. Edit the Text Styles dialog box.
Question 2
You need to select a view that allows you to use the drag-and-drop feature on the resource assignments and unassigned tasks. What should you do?
A. Select the Timeline view.
B. Select the Gantt Chart view, and then click Assign Resources.
C. Select the Team Planner view.
D. Select the Gantt Chart view, split the window, and then select the Resource Usage view for the details pane.
Question 3
You need to ensure that when you add new tasks, the project schedule doesn't set a start date and end date. What should you do?
A. On the Schedule tab of the Project options, change the New tasks created option to Manually Scheduled.
B. On the Advanced tab of the Project options, clear the Automatically add new resources and tasks check box.
C. Click New Tasks and change the option to Auto Scheduled.
D. On the Display tab of the Project options, clear the Edits to start and finish dates check box.
E. Select Task from the main ribbon menu. Highlight the task that you want to change and select Manually Schedule.
Question 4
You have an unscheduled, unassigned task in your Project Professional 2010 schedule. You identify an available resource. You need to assign the task to the resource without scheduling the task. What should you do?
A. Use the Team Planner view.
B. Use the Add Resources function.
C. Use the Calendar view.
D. Use the Replace feature in the Assign Resources dialog box.
Question 5
You have a list of tasks in Microsoft Excel 2010. You need to create a Microsoft Project 2010 schedule that maintains the order of the tasks. Which two actions could you perform? (Each correct answer presents a complete solution. Choose two.)
A. From Project 2010, use the New from Excel workbook wizard.
B. From Excel 2010, save the file by using the .mpt file extension.
C. From Excel 2010, save the file by using the .mpp file extension.
D. From Project 2010, use the Open command and select the Excel file.
Solutions:
| Question 1 Answer: A | Question 2 Answer: C | Question 3 Answer: A | Question 4 Answer: A | Question 5 Answer: A,D |