Pass SAP C-TS422-2504 Exam Info and Free Practice Test
New 2026 Latest Questions C-TS422-2504 Dumps - Use Updated SAP Exam
NEW QUESTION # 37
What happens when you set up detailed scheduling with the finite scheduling mode Insert Operation?
- A. Operations on multi-resources are planned finitely in a sequence.
- B. Sequencing on multi-activity resources is automatically updated during planning.
- C. An operation is scheduled as close as possible to the desired date.
- D. To create a slot, neighbouring operations are moved in both planning directions.
Answer: C
NEW QUESTION # 38
What are some benefits of planning with planned independent requirements for finished materials?
Note: There are 2 correct answers to this question.
- A. Manufacturing time for final assembly is reduced.
- B. You have the option to use make-to-order production.
- C. The delivery time is reduced.
- D. You have the option to use forecast planning.
Answer: B,D
NEW QUESTION # 39
Mode selection is one of the scheduling options available with Advanced Planning in SAP S/4HANA Cloud Private Edition. When can you use mode selection?
- A. When several production versions are maintained for one product
- B. When alternative resources are used within one operation
- C. When several operations are maintained for one product
- D. When multiple planned orders are scheduled in parallel on one resource
Answer: B
NEW QUESTION # 40
What will happen in the MRP run if you have created a new MRP-relevant material that supports both in-house production and external procurement?
- A. The MRP run starts with external procurement.
- B. The MRP run starts with in-house production.
- C. The MRP run does NOT consider the material; it has to be planned interactively.
- D. The MRP run plans the material only if a quotation has been maintained.
Answer: B
NEW QUESTION # 41
What determines whether the planned independent requirements in dem management are consumed by other requirements? Note: There are 2 correct answers to this question.
- A. Requirements profile
- B. Order type
- C. Requirements type
- D. Planning strategy
Answer: C,D
NEW QUESTION # 42
Your company produces a finished good based on a forecast expects it to be in stock when customers order it. If customers order more than the forecasted quantity this must NOT have any impact on the production program.
Which planning strategy do you use?
- A. Assembly processing with production orders (82)
- B. Maketostock production (10)
- C. Planning with final assembly (40)
- D. Planning without final assembly (50)
Answer: B
NEW QUESTION # 43
Which chart types does the tabular planning table for capacity planning provide in SAP S/4HANA Cloud Private Edition?
Note: There are 2 correct answers to this question.
- A. Capacity requirements chart
- B. Orders (dispatched) chart
- C. Work center capacities chart
- D. Order (pool) chart
Answer: A,C
NEW QUESTION # 44
You are a consultant on an SAP S/4HANA Cloud greenfield project.
Which of the following aspects should you focus on to achieve and maintain clean core data quality? Note: There are 2 correct answers to this question.
- A. Timeliness
- B. Efficiency
- C. Accuracy
- D. Stability
Answer: B,D
NEW QUESTION # 45
Which settings can you make in a production scheduling profile?
Note: There are 3 correct answers to this question.
- A. Automatic release on order creation
- B. Automatic print on order creation
- C. Automatic goods receipt on confirmation
- D. Default order types
- E. Automatic goods issue on confirmation
Answer: A,C,D
NEW QUESTION # 46
Which time elements are relevant for lead time scheduling of a production order?
Note: There are 2 correct answers to this question.
- A. Opening period
- B. Total replenishment lead time
- C. Float after production
- D. Setup time
Answer: C,D
NEW QUESTION # 47
You have a scheduling agreement with a vendor. You want classic MRP to automatically create schedule lines in case of a material shortage. What must you do?
Note: There are 2 correct answers to this question.
- A. Set the creation indicator for delivery schedule lines on the initial screen of the MRP run.
- B. Add the agreement to the source list and mark it for MRP relevance.
- C. Add the agreement to the quota arrangement and mark it for MRP relevance.
- D. Set the creation indicator for purchase requisitions on the initial screen of the MRP run.
Answer: A,B
NEW QUESTION # 48
What does the material type influence?
Note: There are 2 correct answers to this question.
- A. Which material master screens appear in which sequence
- B. Which plantspecific plantindependent statuses are allowed
- C. Whether the material is produced inhouse procured externally or both
- D. Which document types class categories are allowed
Answer: A,D
NEW QUESTION # 49
You use the Finite Scheduling - with Reverse planning strategy and want to allow scheduling in the past.
How can you parameterize this in the strategy profile?
- A. Specify a negative PP/DS horizon
- B. Specify a negative opening period
- C. Specify a negative planning horizon
- D. Specify a negative offset time
Answer: D
NEW QUESTION # 50
What is a prerequisite for the consumption of planned independent requirements to take place for planning strategy 40 (Planning with final assembly)?
- A. MRP creates a dependent requirement.
- B. A sales order is delivered.
- C. MRP creates a planned order.
- D. A sales order is created.
Answer: D
NEW QUESTION # 51
Which master data fields can have an impact on whether MRP creates planned orders or purchase requisitions for a material? Note: There are 2 correct answers to this question.
- A. MRP type
- B. MRP group
- C. Material type
- D. Procurement type
Answer: C,D
NEW QUESTION # 52
Which of the following are features of the clean core dashboard? Note: There are 2 correct answers to this question.
- A. It can be accessed by using SAP For Me.
- B. Customers can grant access to the dashboard to partners.
- C. It can be used in all SAP S/4HANA Cloud editions.
- D. Customers can use the dashboard in the dev test production tenants.
Answer: A,B
NEW QUESTION # 53
What determines whether the planned independent requirements in demand management are consumed by other requirements? Note: There are 2 correct answers to this question.
- A. Requirements profile
- B. Order type
- C. Requirements type
- D. Planning strategy
Answer: C,D
NEW QUESTION # 54
What could be the reason for multiple commitments where several operations have the same scheduled dates on a work center after dispatching? Note: There are 2 correct answers to this question.
- A. The Change Planning Direction indicator is set in the strategy profile.
- B. The work center has several individual capacities.
- C. Alternative work centers are fully occupied.
- D. The Finite Scheduling indicator is NOT set in the strategy profile.
Answer: B,D
NEW QUESTION # 55
......
Latest C-TS422-2504 Exam Dumps SAP Exam: https://www.real4dumps.com/C-TS422-2504_examcollection.html
Pass SAP C-TS422-2504 PDF Dumps Recently Updated 89 Questions: https://drive.google.com/open?id=1TS8CPBOA9A6nVhat6UlJylId6yaQLQ5G