NEW QUESTION 14
You are adding a value-based filter to a planning view. Which of the following conditions apply? Note:
There are 3 correct Answers to this question.

  • A. These filters are always applied based on the values stored in the database.
  • B. You can only apply one value-based filter per planning view.
  • C. The alerts dashboard is not available if a value-based filter is set for the open planning view.
  • D. These filters can be used together with attribute totals in the same planning view.
  • E. You can add (or delete) planning objects to a planning view after these filters are applied.

Answer: A,B,C

 

NEW QUESTION 15
Which supply chain challenge is addressed by SAP IBP for demand?

  • A. Inability to respond to short-term changes in supply and demand
  • B. Inability to understand and shape actual demand
  • C. Inability to arrive at consensus demand
  • D. Inability to synchronize supply and demand

Answer: B

 

NEW QUESTION 16
You create a planning filter using an SAP IBP Fiori app. Which of the following objects can it be applied to? Note: There are 2 correct Answers to this question.

  • A. Planning view templates in the SAP IBP add-in for Microsoft Excel
  • B. Snapshot operator in the SAP IBP add-in for Microsoft Excel
  • C. Supply chain graph in Supply Chain Network app
  • D. Jobs in the Applications Jobs app

Answer: A,D

 

NEW QUESTION 17
You are configuring disaggregation for the KF1 key figure. Which methods can you apply? Note: There are 3 correct Answers to this question.

  • A. Disaggregation according to an equal split
  • B. Proportional disaggregation by using KF2 in the expression
  • C. An internal system-generated disaggregation
  • D. Disaggregation in batch triggered by an application job
  • E. Disaggregation according to a user-defined expression

Answer: A,B,E

 

NEW QUESTION 18
How can you make charts and dashboards private?

  • A. Enable the relevant settings in the global configuration parameters.
  • B. Enable the relevant settings in the Analytics Advanced and Dashboards Advanced applications.
  • C. Set restrictions for charts in the Permission filter application.
  • D. Choose only relevant key figures and filters in the Analytics Advanced application.

Answer: A

 

NEW QUESTION 19
You are invited to review a problem with a customer's SAP IBP Excel template performance. What areas with the biggest potential performance impact would you focus on? Note: There are 2 correct Answers to this question.

  • A. Excessive IBP formatting in Excel UI
  • B. Number of local members and complexity of calculations
  • C. Complex calculation graphs for key figures
  • D. Number of analytics charts displaying key figures' values

Answer: A,C

 

NEW QUESTION 20
Which of the following solutions are feasible when using the time series supply optimizer? Note: There are 3 correct Answers to this question.

  • A. Violation of minimum resource utilization
  • B. Violation of minimum aggregated inventory values
  • C. Not respecting production capacity
  • D. Not adhering to maximum transport values
  • E. Not-fully satisfied demands

Answer: A,B,E

 

NEW QUESTION 21
Which of the following data can be tracked using a change-history-enabled key figure? Note: There are 3 correct Answers to this question.

  • A. Scenario ID
  • B. Attributes
  • C. Key figure type
  • D. Reason code
  • E. Modified date

Answer: B,D,E

 

NEW QUESTION 22
You want to display and edit data in different units of measure (UOM). Which of the following must you consider before you use UOM? Note: There are 3 correct Answers to this question.

  • A. Analytics provide the user with the option to select the target unit of measure.
  • B. Conversion to the target unit of measure is handled by functionality of SAP IBP Excel UI
  • C. Unit of measure is an attribute of a master data type, such as Product.
  • D. Units of measure are usually not time-dependent.
  • E. Units of measure are usually not time-independent.

Answer: A,C,D

 

NEW QUESTION 23
What actions can be performed in the Advanced Dashboards application? Note: There are 3 correct Answers to this question.

  • A. Rename the charts.
  • B. Add process templates.
  • C. Link two analytics charts.
  • D. Organize charts.
  • E. Display all assigned analytics on a single UI.

Answer: B,D,E

 

NEW QUESTION 24
Which of these conditions must be met to create a Local Member key figure?

  • A. A key figure is selected in the Key Figures tab in the Microsoft Excel add-in.
  • B. Use Excel Cell References in Report Editor is selected.
  • C. Activate Local Member Recognition is selected.
  • D. A key figure is created in the Planning Area app.

Answer: C

 

NEW QUESTION 25
While modeling for a large machine with high capital needs, you need it to run cost effectively with minimum utilization, even if it means producing more than demand. Which solution would apply to this scenario? Note: There are 2 correct Answers to this question.

  • A. Capacity leveling will be possible for production and storage resources.
  • B. Excess stock can be generated and will need to be staged in an overflow warehouse.
  • C. Balance can be achieved between excessive prebuild and minimum utilization by incorporating violation costs.
  • D. Enough demands can be pulled forward and pull production will occur.

Answer: C,D

 

NEW QUESTION 26
You are modeling the introduction of a new product using Lifecycle Planning functionality in SAP IBP.
What is mandatory to create in your planning area for the setup of reference product(s) to work? Note:
There are 2 correct Answers to this question.

  • A. Definition of an attribute representing the product description
  • B. Definition of an attribute representing the product ID
  • C. Definition of Actual Sales business meaning for one key figure
  • D. Planning objects for the new product

Answer: B,D

 

NEW QUESTION 27
What is a prerequisite for modeling outsourced manufacturers with production capacity?

  • A. Ensure that multiple modes of transportation are set up.
  • B. Use production lead times and offsets to manage components at the outsourced location.
  • C. Model production costs for internal and external production resources to model priority.
  • D. Model target inventory and stocks at the outsourced location.

Answer: C

 

NEW QUESTION 28
You are reviewing the master data types for supply planning. Which master data types are compound master data types? Note: There are 2 correct Answers to this question.

  • A. SOURCECUSTOMER
  • B. SOURCEPRODUCTION
  • C. LOCATIONFR
  • D. SOURCELOCATION

Answer: A,D

 

NEW QUESTION 29
When can filter blocks appear in calculations? Note: There are 2 correct Answers to this question.

  • A. When using IFISNULL statements in the formula
  • B. When modeling cross-period calculations
  • C. When modeling attribute transformations
  • D. When modeling attribute as a key figure

Answer: B,C

 

NEW QUESTION 30
You create an S&OP operator for heuristics on an SAP IBP project. What must you enable for the S&OP operator that is specifically relevant for subnetworks?

  • A. Supply propagation
  • B. Normalize Quotas parameter
  • C. Balance Receipts parameter
  • D. Compute Expected Supply parameter

Answer: D

 

NEW QUESTION 31
Which of the following are the key features of SAP Supply Chain Control Tower? Note: There are 2 correct Answers to this question.

  • A. Ability to create a feasible plan
  • B. Ability to use task and case management
  • C. Ability to balance demand and supply and attain financial targets
  • D. Ability to create smart alerts

Answer: B,D

 

NEW QUESTION 32
You need to define a new logic for a key figure to drive values from the PERPRODCUSTREGION level to the PERPRODCUST level. Which of the following configuration options are possible for this process?
Note: There are 2 correct Answers to this question.

  • A. Splitting the values from aggregated to detailed level based on time profile attribute
  • B. Splitting the values from aggregated to detailed level based on stored split-factor key figure
  • C. Splitting the values from aggregated to detailed level using multiplication by the proportions
  • D. Splitting the values from detailed to aggregated level by using copy operator

Answer: B,C

 

NEW QUESTION 33
Which of the following can be used as inputs for inventory level optimization? Note: There are 2 correct Answers to this question.

  • A. Lot sizes
  • B. Reorder point
  • C. Target inventory level
  • D. Lead time variability

Answer: A,D

 

NEW QUESTION 34
What are S&OP operator (optimizer) parameters associated with demand fair share?

  • A. Number of fair share segments. Additional tiering costs (default). Target inventory violation cost
  • B. Number of fair share segments. Maximum days of coverage. Number of fair share segments late delivery
  • C. Number of fair share segments. Maximum inventory. Additional tiering costs (default)
  • D. Number of fair share segments. Additional tiering costs (default). Number of fair share segments late delivery

Answer: D

 

NEW QUESTION 35
Which of the following modes can you use when creating a constrained plan? Note: There are 2 correct Answers to this question.

  • A. Delivery maximization
  • B. Production maximization
  • C. Profit maximization
  • D. Resource maximization

Answer: A,C

 