NEW QUESTION # 44
Where can you create a status for a what-if scenario in portfolio management/
- A. In customizing for the portfolio type
- B. In the what-if scenario classification
- C. In the review
- D. In the what-if scenario type
Answer: A
NEW QUESTION # 45
A WBS element has been created automatically for a project management project. A change is made to the organizational unit of the project definition.
When is the master data of the internal order updated with the change?
- A. Upon the next transfer
- B. Upon release of the WBS element
- C. Upon the next cost planning run
- D. Upon release of the project
Answer: A
NEW QUESTION # 46
You have defined a financial view for portfolio bucket so that financial values are rolled up.
Which of the following are possible sources for the rollup?
NOTE: There are 3 correct answers to this question
- A. Standalone items
- B. Project system project
- C. Initiatives
- D. Project management projects
Answer: A,C
NEW QUESTION # 47
What can you use scoring models for?
NOTE: There are 2 correct answers to this question.
- A. To derive field values of items
- B. To derive field values of buckets
- C. Top compare items in reviews
- D. To compare bucket in reviews
Answer: A,C
NEW QUESTION # 48
Your client wants to add additional checklist items to a project that has already began. They want to control the items separately as unplanned.
Which setting must you make in customizing?
- A. Create a checklist item type and assign to the project type
- B. Create a checklist type and assign a new status Unplanned
- C. Create a checklist type and set the issue list indicator
- D. Create a checklist item type and set the issue item indicator
Answer: C
NEW QUESTION # 49
You have assigned two resources to the same role resource 1 to calendar week 10 and resource 2 to calendar week 11. You want to re-assign resource 2 to calendar week 10 bar the system does not allow you to do so.
What could be a reason for the system behavior?
- A. The flexible Assignment indicator is active for the rile type in customizing
- B. The role demand for the timeframe is too low
- C. The assigned effort for either of the resource assigned is to high
- D. The edit in parallel indicator is inactive for the role type in customizing
Answer: D
NEW QUESTION # 50
Which of the following are basic parts of SAP innovation management?
NOTE: There are 2 correct answers to this question.
- A. Idea community
- B. Innovation office
- C. Mobile web app
- D. Opportunity overview
- E. Portfolio Review
Answer: A,B,C
NEW QUESTION # 51
Which of the following object help to support automatic creation between portfolio and project management (PPM) and project system (PS)?
NOTE: There are 2 correct answers to this question
- A. PS network
- B. PS profile
- C. PS operative project
- D. PS standard project
Answer: B,C
NEW QUESTION # 52
What can you define in the item template?
- A. Link to a project management project
- B. Sequence of decision points
- C. Financial planning
- D. Category
Answer: D
NEW QUESTION # 53
What is a prerequisite for using role charts in project management?
- A. A graphic profile is assigned to the project type
- B. A graphic profile is assigned to the role type
- C. The demand of a role must have been updated according to tasks
- D. The demand of a role must be distributed over a number of periods
Answer: D
NEW QUESTION # 54
What features does SAP analytics cloud deliver in combination with SAP PPM?
NOTE: There are 3 correct answers to this question.
- A. Intelligent algorithms highlighting possible data quality issues and distributing your data
- B. Provides models for financial and capacity planning
- C. Smart transformations enabling you to quickly address and solve data quality issues
- D. Out-of-the-box cost commitment reporting capabilities
- E. Built-in connectors to data sources
Answer: A,C,E
NEW QUESTION # 55
What is the priority field in the project definition of a project management project used for?
- A. To determine the approval authorizations required
- B. To support the evaluation of projects
- C. To determine the scheduled dates for the project
- D. To restrict the selection of project types
Answer: B
NEW QUESTION # 56
Which information can be assigned to a business partner in project management?
NOTE: There are 3 correct answers to this question
- A. Personal numbers
- B. Production resources or tools (PRT)
- C. Areas and locations
- D. SAP users
- E. Work centers
Answer: A,C,D
NEW QUESTION # 57
Which of the following are search criteria In Resource Search in Project Management?
NOTE: There are 2 correct answers to this question.
- A. Organizational units
- B. Qualifications
- C. Work centers
- D. plants
Answer: A,B
NEW QUESTION # 58
You want to confirm your work hours to tasks with the cross-Application time sheet (SAP CATS). When you enter the time sheet (CAT2) your list is empty.
What could be the reason for this?
NOTE: There are 2 correct answers to this question.
- A. Your role and business partner are assigned to tasks that have the in process status
- B. Your role and business partner are assigned to task that have the created status
- C. Your user is not assigned to a business partner
- D. Your personal number is not assigned to a business partner
Answer: B,D
NEW QUESTION # 59
You want to distribute capacity requirements in a project management project?
How can you distribute the values?
NOTE: There are 3 correct answers to this question
- A. Enter the vales manually
- B. Apply a distribution rule
- C. Use a distribution function
- D. Copy values from resource assignments
- E. Update the capacity requirements from the roll-up of task requirements
Answer: A,C,E
NEW QUESTION # 60
Which of the following are valid breakdown periods for financial planning in Portfolio Management? Note: There are 2 correct answers to this question
- A. 2 weeks
- B. 1 year
- C. 10 days
- D. 3 months
Answer: B,D
NEW QUESTION # 61
Which objects can used to record times in Cross-Application Time Sheels (SAP Cats)?
NOTE: There are 3 correct answers to this question
- A. Task
- B. Checklist item
- C. Phase
- D. Role
Answer: A,D
NEW QUESTION # 62
In a existing project management project, all objects have been released and all subordinate tasks for the checklist items have been completed.
Why does the status change fail when you try to set the status of the checklist to Finish?
How can you trigger a workflow for a portfolio item?
- A. A checklist item is still open
- B. The checklist item result is set to not ok
- C. At least of the tasks has been configured
- D. You are missing the authorization for changing the project
Answer: B,D
NEW QUESTION # 63
......