NEW QUESTION 52
Which of the following plant is used in the production process, where few raw materials can be made into several end products?

  • A. I-plant
  • B. A-plant
  • C. V-plant
  • D. G-plant

Answer: C

 

NEW QUESTION 53
The absence of defects both in product and non-product categories and use of a good documentation system, this is known as:

  • A. Maintainability
  • B. Official recognition
  • C. Sustainability
  • D. supplier certification

Answer: D

 

NEW QUESTION 54
The purpose/s of rough-out capacity planning is /are:

  • A. Ensure utilization of work centers and advice vendors of capacity requirements
  • B. provide warnings of any bottlenecks
  • C. to check the feasibility of the MPS
  • D. All of these

Answer: D

 

NEW QUESTION 55
Which of the following is NOT the method of forecasting?

  • A. quantitative
  • B. extrinsic
  • C. intrinsic
  • D. qualitative

Answer: A

 

NEW QUESTION 56
With reference to the above example; if the cost of carrying inventory is $5 per case based on ending inventory, what is the total cost of carrying inventory?

  • A. $2900
  • B. $3000
  • C. $2300
  • D. $2200

Answer: C

 

NEW QUESTION 57
Basic strategies that can be used in a production plan may be:

  • A. Any one of these
  • B. Subcontracting
  • C. Production leveling strategy
  • D. Chase strategy

Answer: A

 

NEW QUESTION 58
When a quantity of an item equal to the order point quantity is set aside and not touched until all the main stock is used up, this strategy is called:

  • A. Dual system
  • B. Wait-for-next strategy
  • C. Two-fold system
  • D. Two-bin system

Answer: D

 

NEW QUESTION 59
Continuous improvement does not focus on a "one-shot" improvement out on such things as:

  • A. Rate on improvement in quality
  • B. Reliability, innovation, effectiveness and productivity
  • C. Cost and cost
  • D. All of these

Answer: D

 

NEW QUESTION 60
The process of placing the exploded requirements in their proper periods based on lead time is called

  • A. Where-used reports
  • B. Offsetting
  • C. Production plan
  • D. Exploding the equipments

Answer: B

 

NEW QUESTION 61
Manufacturing process can be conveniently organized into following categories EXCEPT:

  • A. Intermittent Manufacturing
  • B. Work Center Manufacturing
  • C. Flow Manufacturing
  • D. Project Manufacturing

Answer: B

 

NEW QUESTION 62
The carrying cost is usually defined as a percentage of the dollar value of inventory per unit of time.

  • A. True
  • B. False

Answer: A

 

NEW QUESTION 63
An open order appears as a/an on the MRP.

  • A. Scheduled receipt
  • B. Order releases
  • C. Open order file
  • D. None of these

Answer: A

 

NEW QUESTION 64
Capacity is the quantity of work done and not the rate of doing work.

  • A. True
  • B. False

Answer: B

 

NEW QUESTION 65
Dependency in MRP can be

  • A. None of the above
  • B. Horizontal
  • C. Vertical
  • D. Both A & B

Answer: D

 

NEW QUESTION 66
Demonstrated capacity is:

  • A. Minimum output
  • B. Average Output
  • C. Maximum output
  • D. None of these

Answer: B

 

NEW QUESTION 67
The tracking signal can be calculated as:

  • A. Tracking signal = algebraic sum of forecast errors / MAD where MAD = Mean Absolute Deviation
  • B. Tracking signal = algebraic sum of forecast orders / MAD
  • C. Tracking signal = cumulative sum of forecast errors * MAD
  • D. Tracking signal = cumulative sum of forecast errors + MAD

Answer: A

 

NEW QUESTION 68
Following figure shows: (draw here figure 4.10) with out mentioning names)

  • A. Production requirements
  • B. Pegged requirement
  • C. Summarized part lists
  • D. Where-used reports

Answer: B

 

NEW QUESTION 69
What consists of taking a sample of a batch of product and using it to estimate the overall quality of the batch?

  • A. Acceptance sampling
  • B. Analytical sampling
  • C. Statistical sampling
  • D. Batch sampling

Answer: A

 

NEW QUESTION 70
A difference between the physical count and inventory dollars for the inventory records is called:

  • A. Provocation
  • B. Resolution
  • C. Accuracy
  • D. Reconciliation

Answer: D

 

NEW QUESTION 71
Planning file/s needed for the production activity control is/are:

  • A. Product structure file
  • B. Routing and work center master file.
  • C. All of these
  • D. Item master file

Answer: C

 

NEW QUESTION 72
The sum of the benefits the customer receives and can be more than the product itself is called:

  • A. value
  • B. price
  • C. quality
  • D. workforce

Answer: A

 

NEW QUESTION 73
products. is concerned with the production of high-volume standard

  • A. None of the above
  • B. Repetitive manufacturing
  • C. Flow manufacturing
  • D. Continuous manufacturing

Answer: C

 

NEW QUESTION 74
Which event usually focuses on a fairly small part of the overall producti0on process to improve that part of the process?

  • A. Build
  • B. Allen
  • C. Kaizen
  • D. Fair

Answer: C

 

NEW QUESTION 75
......


APICS CPIM Exam Syllabus Topics:

TopicDetails
Topic 1
  • Basics of Supply Chain Management
Topic 2
  • Master Planning of Resources
Topic 3
  • Strategic Management of Resources.

 

Pass APICS CPIM Exam Quickly With Real4dumps: https://www.real4dumps.com/CPIM_examcollection.html

CPIM Dumps - The Sure Way To Pass Exam: https://drive.google.com/open?id=1Lo0YNdgEgsiTzoVjxK7HEYvUFlISlN-1