[Q133-Q158] CPIM Free Update With 100% Exam Passing Guarantee [2021]

Share

CPIM Free Update With 100% Exam Passing Guarantee [2021]

[Oct-2021] Verified APICS Exam Dumps with CPIM Exam Study Guide

NEW QUESTION 133
Which of the following are the two sources of specifications?

  • A. Standard specification & Engineering specification
  • B. Seller specification & Standard specification
  • C. Buyer specification & Standard specification
  • D. Buyer specification & Buyer specification

Answer: C

 

NEW QUESTION 134
Economic regulation has centered on which of the following areas?

  • A. All of the above
  • B. Control of routes and service levels
  • C. Control of market entry and exit
  • D. Regulations of rates

Answer: A

 

NEW QUESTION 135
Which of the following are the purposes of material requirement planning so items in the master production schedule are made on time?

  • A. To determine the quantities
  • B. All of the above
  • C. To determine the components needed
  • D. To determine the due dates

Answer: B

 

NEW QUESTION 136
Which one of the following statements is about capacity requirements planning?

  • A. Both A&B
  • B. Involves translating monthly, quarterly or annual product priorities from the production plan into some total measure of capacity, such as gross labor house.
  • C. This type of planning focuses on components parts, grater detail is involved than in roughcut capacity planning.
  • D. It is directly liked to the material requirements plan

Answer: A

 

NEW QUESTION 137
The sum of the benefits the customer receives and can be more than the product itself is called:

  • A. price
  • B. quality
  • C. value
  • D. workforce

Answer: C

 

NEW QUESTION 138
Which forecast performance measure detects bias?

  • A. tracking signal
  • B. MAPE
  • C. MAD
  • D. standard deviation

Answer: A

 

NEW QUESTION 139
What is based on a comparative analysis of the introduction and growth of similar products in the hope that the new product behaves in a similar fashion?

  • A. Historical analogy
  • B. Future analogy
  • C. Estimated analogy
  • D. Forecasting analogy

Answer: A

 

NEW QUESTION 140
The order picker circulates throughout the warehouse selecting the items on the order through:

  • A. Area system
  • B. Zone system
  • C. Pick and choose system
  • D. Managing system

Answer: A

 

NEW QUESTION 141
What may vary depending upon the interest rates, the credit rating of the firm, and the opportunities the firm may have for investment?

  • A. Item cost
  • B. Capital cost
  • C. Inventory cost
  • D. Normal cost

Answer: B

 

NEW QUESTION 142
A company ships a particular product to a market located 1000 miles from the plant at a cost of $4 per mile. Normally it ships 500 units at a time. If the company can ship the units unassembled, it can ship 800 units in a truck. What is the line-haul cost per unit now?

  • A. $4
  • B. $8
  • C. $5
  • D. $10

Answer: C

 

NEW QUESTION 143
Which of the following are those of space and materials handling equipment?

  • A. Equipment costs
  • B. Material costs
  • C. Capital costs
  • D. Variance costs

Answer: C

 

NEW QUESTION 144
The flow of work centers must be planned to meet delivery dates which means production activity control must do the following:

  • A. Schedule start and completion dates for each shop order at each work center so the scheduled completion date of the order can be met. This sill involves a planner in developing a load profile for the work centers.
  • B. Ensure that the required materials, tooling, personnel and information are available to manufacture the components when needed.
  • C. None of these
  • D. Both of these

Answer: D

 

NEW QUESTION 145
An index of the relative priority of an order to other orders at a work center is referred to as:

  • A. Aspect ratio
  • B. Priority ratio
  • C. Critical ratio
  • D. Schedule ratio

Answer: C

 

NEW QUESTION 146
The movement and storage of finished goods from end of production to the customer is called:

  • A. Physical supply
  • B. Physical associate
  • C. Physical distribution
  • D. Physical channel

Answer: C

 

NEW QUESTION 147
An open order appears as a/an on the MRP.

  • A. Open order file
  • B. Order releases
  • C. None of these
  • D. Scheduled receipt

Answer: D

 

NEW QUESTION 148
is difference between the total planned for a given period and the
actual total for that period.

  • A. Total control rate
  • B. Collective concern
  • C. Increasing rate
  • D. Cumulative variance

Answer: D

 

NEW QUESTION 149
The files contained in the database are of two types which are:

  • A. planning and control
  • B. absolute and relative
  • C. planning and procedural
  • D. fixed and variable

Answer: A

 

NEW QUESTION 150
What determines the basic processes needed to convert the raw materials and components sinto the finished product?

  • A. Process development
  • B. All of the above
  • C. Product's design
  • D. Product's manufacturing

Answer: C

 

NEW QUESTION 151
Total customer satisfaction based on the complete experience with an organization, not just the product is known as:

  • A. Total quality
  • B. Perceived quality
  • C. Absolute quality
  • D. Fool proof quality

Answer: B

 

NEW QUESTION 152
MPS is meant to be:

  • A. Depends on situation
  • B. cyclic
  • C. Flexible
  • D. Rigid

Answer: C

 

NEW QUESTION 153
Which of the following is NOT the class of activity?

  • A. Environment
  • B. Operation
  • C. Inspection
  • D. Storage

Answer: A

 

NEW QUESTION 154
What serves as a means of identifying the product in a way not possible from its outward appearance?

  • A. Container
  • B. Frontier
  • C. Boundary
  • D. Package

Answer: D

 

NEW QUESTION 155
The advantage/s of production leveling is/are:

  • A. All of these
  • B. It results in smooth level off operation that avoids the costs of changing production levels.
  • C. Firms do not need to have excess capacity to meet peak demand
  • D. Firms do not need to hire and train workers and lay them off in slack periods

Answer: A

 

NEW QUESTION 156
shows the quantities needed and when manufacturing intends to make use or use them.

  • A. Production plan
  • B. Purchasing and production activity control
  • C. MPS
  • D. Material Requirement Plan

Answer: D

 

NEW QUESTION 157
The old saying "What you do not measure, you cannot control", is as valid today as it was when first stated. The necessary step/s in implementing a successful performance measurement program is/are:

  • A. All of these
  • B. State the measurement to be used, set performance standards, educate the user and make sure the program is consistently applied
  • C. Define performance
  • D. Establish company goals and objectives

Answer: A

 

NEW QUESTION 158
......

Authentic Best resources for CPIM Online Practice Exam: https://www.real4dumps.com/CPIM_examcollection.html

CPIM Test Engine Practice Exam: https://drive.google.com/open?id=1Lo0YNdgEgsiTzoVjxK7HEYvUFlISlN-1